Thursday, September 13th (beginning at 6:00 pm)

  • First from Church to Cedar at Second will be CLOSED TO MOTORIST; OPEN TO PEDESTRIANS.  We have attempted to keep as much of First Ave open as possible while work occurred between Main and Church.  Crews are now moving the project from the block between Church and Main to the blocks north of Main.  Beginning tomorrow morning, parking will no longer be allowed on First Ave north of Main to Second and Cedar.

Friday, September 14th

  • First from Church to Cedar at Second will be CLOSED TO MOTORIST; OPEN TO PEDESTRIANS until 5:00 pm.
  • First from Church to Main will be OPEN TO MOTORIST; OPEN TO PEDESTRIANS after 5:00 pm.
  • First from Main to Cedar at Second will be CLOSED TO MOTORIST; OPEN TO PEDESTRIANS.
  • Cedar Street between Second and Fifth: CLOSED TO MOTORIST; OPEN TO PEDESTRIANS from 7:00 am to 12:00 pm while crews stripe the street, crosswalks, and parking spaces. 

Saturday, September 15th

  • First from Church to Cedar at Second will be CLOSED TO MOTORIST; OPEN TO PEDESTRIANS.  The cornhole tournament will occur between Church and Main.
  • Cedar will be open between Second and Fifth.

Sunday, September 16th

  • First from Main to Cedar at Second will be CLOSED TO MOTORIST; OPEN TO PEDESTRIANS.

Monday – Friday, September 17th – 21st

  • First Ave from Main to Cedar at Second Ave will be CLOSED TO MOTORIST; OPEN TO PEDESTRIANS while crews continue replacing the sewer.
  • Cedar will be open between Second and Fifth with intermittent lane closures for concrete placement and street furniture.

New trees and landscaping will be planted the week of September 24th.

** During our discussions with businesses, we have received several requests for four-way stops to be installed at Cedar/Third and on First/Main.  Staff have reviewed this from a traffic and safety standpoint and concur with this recommendation.  If you have any question or concerns regarding this change, please contact us in the next few days.